El astillero de Fene finaliza el ensamblaje de la primera jacket para el parque eólico de Saint-Brieuc

Ensamblaje primera jacket para Saint Brieuc

Navantia ha concluido, en su astillero de Fene, el ensamblaje final de la primera jacket para el parque eólico marino de Saint-Brieuc, que Iberdrola levanta en la Bretaña francesa.

Este hito constructivo se ha producido tras la recepción del primer lote de componentes fabricados en el puerto de Brest. Los componentes han sido ensamblados a los bloques principales fabricados en Fene por la UTE Navantia-Windar y sus empresas colaboradoras.

Esta maniobra ha sido realizada con una grúa oruga de 1.600 toneladas, debido a las dimensiones y peso de estas jackets, más de 74 metros y 1.100 toneladas.

Paralelamente, ya se encuentran en distintas fases constructivas 40 de las 62 jackets que comprende el contrato con Iberdrola.

En los próximos meses y hasta la entrega de las últimas unidades, prevista para el tercer cuatrimestre de 2022, este programa generará picos de 1.000 empleos en la comarca, además de la carga de trabajo realizada por empresas españolas en el puerto de Brest que ha permitido crear unos 2.000 empleos en la Bretaña.

Saint-Brieuc, con una inversión de 2.400 millones de euros, es el primer proyecto de energía eólica marina de Iberdrola en Francia. El parque, con una potencia total instalada de 496 megavatios (MW), y su producción permitirán el suministro de energía limpia a una población equivalente de 835.000 personas; cerca del 9% del consumo eléctrico total de la Bretaña.

Saint-Brieuc cuenta con una alta participación de empresas españolas en su construcción: los jackets -plataformas que sustentan los aerogeneradores marinos-y los pilotes serán construidos y montados por Navantia-Windar, en Fene (A Coruña) y Avilés (Asturias), respectivamente; los aerogeneradores serán suministrados por Siemens Gamesa y la empresa vasca Haizea Wind llevará a cabo el montaje de las torres.

Ensamblaje primera jacket para Saint Brieuc

Navantia has completed, at its Fene shipyard, the final assembly of the first jacket for the Saint-Brieuc offshore wind farm, which Iberdrola is building in French Brittany.

This construction milestone has occurred after the receipt of the first batch of components manufactured in the port of Brest. The components have been assembled to the main blocks manufactured in Fene by the UTE Navantia-Windar and its collaborating companies.

This maneuver has been carried out with a 1,600 ton crawler crane, due to the dimensions and weight of these jackets, more than 74 meters and 1,100 tonnes.

At the same time, 40 of the 62 jackets included in the contract with Iberdrola are already in different construction phases.

In the coming months and until the delivery of the last units, scheduled for the third quarter of 2022, this program will generate peaks of 1,000 jobs in the region, in addition to the workload carried out by Spanish companies in the port of Brest that has allowed create some 2,000 jobs in Brittany.

Saint-Brieuc, with an investment of 2.4 billion euros, is Iberdrola’s first offshore wind energy project in France. The park, with a total installed power of 496 megawatts (MW), and its production will allow the supply of clean energy to an equivalent population of 835,000 people; about 9% of the total electricity consumption of Brittany.

Saint-Brieuc has a high participation of Spanish companies in its construction: the jackets -platforms that support the offshore wind turbines- and the piles will be built and assembled by Navantia-Windar, in Fene (A Coruña) and Avilés (Asturias), respectively ; the wind turbines will be supplied by Siemens Gamesa and the Basque company Haizea Wind will carry out the assembly of the towers.

jQuery(function($) { $('select').on('change', function() { var url = $(this).val(); if (url) { window.location = url; } return false; }); }); function surfto(form) { var myindex=form.dest.selectedIndex window.open(form.dest.options[myindex].value,"_top","""); }